Content translation/Deployments/Deployment Plan
(Redirected from Content translation/Deployment Plan)
Warning: Please don't modify this page without coordinating with the Wikimedia Language Engineering team members.
Archive
|
---|
Deployment Plan
editGeneral
editDeployment Component | Day/Time | People Involved | Notes |
---|---|---|---|
cxserver | Wednesday (PST)/Thursday (IST), Before CX deployment | Kartik (kart_), Tech Ops (Alex K/Andrew/Fillippo mostly) | See this |
ContentTranslation extension updates | Deployment train | Release Team | This can also be done by SWAT (for cherry-pick) if needed. |
cxserver configuration | As needed | Kartik (kart_), Tech Ops | Puppet config; In effect immediately. |
MediaWiki config in Production | As needed | Kartik (kart_), Niklas (Nikerabbit) | mediawiki-config |
New Language pairs
editAs per the graduation plan and this plan may vary depending upon language pairs and possible complexity in languages and MT availability etc.
Steps | Components Modified | People Involved | Days to complete (estimated) |
---|---|---|---|
Request received | None; Request Triaged | Runa/Amir/Pau | 1 |
Possible language sources checked | None | Runa/Pau | 1 |
Language specific adaptation | cxserver & CX extension. See: checklist | Developers | 0-7 |
MT quality survey completed (applicable for languages with MT support) | None | Runa/Amir/Pau | 3 (may vary depending on community response) |
Configuration update on labs instance for users to test | MT packages (applicable for languages with MT support) cxserver config for language pair |
Kartik/Niklas/TechOps | 3–4 days |
Testing period on Labs | None | Everyone | 7 days |
Announcement made on the Wikipedia VP/Community forum about projected deployment date | None | Runa | 1 (to be done on the same day when testing period starts on Labs |
Preparation for deployment on production instance | Puppet config for new pair mediawiki-config for deployment in new wiki (if needed) and schedule SWAT |
Kartik/Tech Ops | 3–5 days (to be completed by the last day of testing on Labs, if no major bugs are identified) |
Deployment on Production instance | mediawiki-config merged (with SWAT) and updated in the target wikipedia Puppet config merged |
Kartik/Tech Ops | 2 days |
Announcements made to the target Wikipedia | None | Runa | 1 day (same as production deployment) |
Update Analytics data/graph (Limn) | Analytics. See: New language How-to | Kartik/Niklas | To be done along with Production deployment |
Upcoming deployment
edit- By "deployment" we mean "Deploy CX as a beta feature", not as a feature available for everybody.
Code and configuration changes
editPlanned
edit- Apertium:
- Puppet:
- config:
- Content Translation:
- cxserver: