Core Platform Team/Initiative/Unify Parsers-Phase 1/Time and Resource Estimates

< Unify Parsers-Phase 1

Estimated Start Date

Started in FY1819 Q2

Actual Start Date

None given

Estimated Completion Date

None given

Actual Completion Date

None given

Resource Estimates

9-12 months, completion is expected near end of FY1819 Q4 / early FY1920 Q1

3.5 FTE for the duration

Augmenting with 2+ FTE for 3 months

0.5 Engineering and Project Management for the duration

Collaborators
  • Parsing Team
  • Core Platform
  • Performance
  • SRE